Alongside Twelve Acre Drive, trees were cut recently. There are two wide gaps.
The cut trees line up with the access roads in what will become the next North Abingdon development. The development, near Peachcroft Farm, got outline planning permission in 2017 to include 371 residential dwellings, pavilions and sports pitches. More details were made public a year ago at https://www.bellway-northabingdon.co.uk/. That was followed by a detailed application REF=P22/V0680/RM a year ago, which, after discharging several conditions, was approved in February 2023. So work has begun.
I thought that only 250 houses were allowed to be built before the diamond interchange was started.
400 houses are allowed to be occupied from the Abbey Fields site and the Bellway one by Peachcroft farm before the contract is signed to build the diamond interchange (this doesn’t include the Kings Gate development)
“From correspondence with the County Council, Bellway understand that a planning application is expected to be submitted within April this year with construction likely to commence in September.”
Ray, that was April 2022 and construction was due to start in September 2022 but there have been a few delays…0