Category Archives: road works

Summer Gas Works bring Drayton Road Delays


Gas Mains replacement works near the Ock Bridge on Drayton Road are scheduled to run from 4th August 2025 for two weeks. Although the timing coincides with the Summer school holidays, when traffic is usually lighter, the introduction of temporary traffic lights is causing delays.

The impact has not been limited to Drayton Road. St Helen’s Wharf, Marcham Road, Ock Street, and surrounding routes are all seeing slower traffic than usual.

This is part of a wider programme of gas mains replacement work. Drayton Road is known to be one of the more sensitive locations for traffic disruption. Lets hope there is not an accident on the A34 that forces more traffic down that road.

Stop and Go on West St Helen Street


It all started so well this morning with traffic flowing smoothly along West St Helen Street. But by lunchtime, a queue of traffic had slowed to a crawl.

The usual school run chaos is over for a few weeks. Although term officially ends tomorrow (22nd July), many local schools are having inset days on the 21st and 22nd. With staff training underway and students at home, the school year is effectively over.

Even so, by midday, Radio Oxford was reporting traffic problems — not across Oxfordshire, just here in Abingdon. Temporary traffic lights on Ock Street were causing long tailbacks, holding up drivers trying to get out of the town centre via the High Street, and all its tributaries. Radio Oxford said it added twenty minutes to the journey from Culham, and fifteen minutes from West St Helen Street.

One man sitting in his car told me, ‘I’ve lived here since 1978, and the traffic just keeps getting worse.’

By the afternoon, things had quietened down as the temporary lights were switched off. But the lights might be back over the next couple of days.

Lodge Hill A34 Interchange – Progress Update (Summer 2025)


Enabling works are well underway on the Lodge Hill A34 interchange upgrade. Since the earlier blog post announcing the start of construction, more progress has been made – especially on the works depot and car park. This area will eventually link a new roundabout on the A4183 (Oxford Road) with a new slip road onto the southbound A34 towards Newbury, helping to ease traffic through Abingdon.

Further vegetation clearance has taken place near the existing slip road from Oxford. This is in preparation for one of the two new roundabouts. It will connect the slip road from Oxford and the new slip road towards Newbury with the A4183.

There has been some clearance for the other new roundabout. It will connect the new slip road from Newbury and the slip road to Oxford with the A4183.

The main construction work — including the two roundabouts forming the new ‘dumbbell’ layout and south facing slip roads — is due to begin in late summer 2025. As part of the project, the access road to Egertons will be re-routed.

Oxford Road Sewer Works Delayed Again


The contractor working to connect sewers for the new North Abingdon housing had a permit to carry out roadworks on Oxford Road from 28 April to 17 September 2025. However, progress has stalled once again.

The delay follows the discovery of an uncharted water main, which now requires a further redesign in coordination with Thames Water. This comes after an earlier redesign caused the project to be postponed to this summer.

In response, Oxfordshire County Council has cancelled the permit and told the developer to clear the site and return with a revised plan. As a result, it now appears that the works at the Oxford Road roundabout will not be completed any time soon — though this does not affect the A34 interchange, only the Oxford Road and roundabout.

The County Council told the contractor to fully open the road by 23 June. As this deadline has not been met (see picture from today – 25 June 2025), overrun penalties now apply:
* £5,000 per day for the first three days
* £10,000 per day thereafter

The County Council has pointed out that the work has broken some of the agreed rules of the permit, including:
* No one was on site to manage traffic by hand when needed
* Work was done outside the allowed hours
* A safe temporary crossing for pedestrians wasn’t provided
* There were long periods with no work happening and no explanation given

The Council has made it clear that while essential infrastructure work is supported, it must be done responsibly, transparently, and to a high standard.

County and Town Councillors and Highways Officers have played a role in pressing for a new plan for the works and fully opening the road.